Completed foundation

Preparing home site for new foundation

Dug basement ready to start footings Pouring footings Footings ready to set wall forms Setting wall forms for foundation Pouring foundation Pouring foundation Completed FoundationRead More»
IMG 5551

Clearcrest Subdivision

To renovate the former golf course into a residential subdivision, O’Risky Excavating constructed roadways and treated them with a process called Lime Stabilization.  Lime Stabilization is completed to help dry out and stabilize the dirt in preparation for Asphalt, Concrete or Gravel, to be placed over the dirt to create a working roadway.

Read More»
Clearing 3

Clearing for Access Driveway and Future Home

This was a very challenging project from the start.  The very rough terrain included a 150’ vertical drop that had to be formed into a manageable slopped driveway down to home site.  All site utilities had to be jack hammered underground and sleeved for adequate protection from rock damage.

Read More»
Septic System Tank Installation

Residential Septic System (Per Vand. County Septic System Requirments)

Upon completion of the septic system installation, you will receive a detailed booklet about care, maintenance, and “dos and don’ts”. In order to keep your septic system in top performance, it is important to have it serviced annually. Contact us to set up your annual Septic System Inspection.

1500 gallon septic tank and 1000 gallon dosing tank Presby Bed w/(3) 85′Read More»
IMG 20200806 112728

Solarbron Senior Living Spillway Repair

Repair and replace approximately 100′ of 12″ HDPE Pipe

Read More»
IMG 1035

9 Acre Lake in Western Kentucky

October 2017 June 2018 Sept. 2018 October 2020 October 2020

Read More»
Perry Heights

EVSC – Perry Heights Storm Water Drainage Repair

Working closely with local engineers Morley & Associates to repair and improve drainage issues in the parking lot

Read More»
IMG 20201203 061938423

Presby 1000 Gal. Septic System & Dosing Tank

Install (4) 52.5′ Presby Pipe Per Vanderburgh County Code. Note: Stakes hold Presby pipe in place until sand is installed over top. Install (4) 52.5′ rows of Presby Pipe Finishing a Presby Field Bed.
High and Low Vents are necessary in septic systems with a dosing tank to allow the bacteria to breathe.Read More»
Under 2K Single-Family Residential Foundation Award

Under 2K Single-Family Residential Foundation Award

Tales of the Tape:

  • Linear Feet of Wall: 300
  • Square Feet: 1,920
  • Yards of Concrete: 375
  • Steel Reinforcement: 17,500 lbs.
  • Wall Heights: 14’-0”
  • Wall Thickness: 10”
  • Steel Beams: 10,000 lbs.
  • Excavation Mass: 10,000+ cubic yards
  • Backfill: 5,000 lbs.
Read More»

Lake updates

Aerial view of lake constructionRead More»
1 2 3 5